ATB700 Fully Threaded
Bar & 'AT' Rockbolts
Double Twisted
Hexagonal PVC
Coated Mesh
Composite Self Drilling
Soil Nails
FT500 Fully Threaded
Composite Bar & Tube
Self Drilling Steel
Anchor System
Turmag Drilling Machine
Welded Mesh
Fibre Mesh
 

  CIVILS
  
  Conisbrough Tunnel
  PorthKerry Tunnels
  The Bradway Tunnel
  Athens Metro
  Glenholt Tunnel
  Conway Castle
  The Sidmouth Cliffs
  A5 - North Wales
  Brokenberry Quarry
  Tondu Iron Works
  Chatham Dock
  A638 Rocknetting
  Blaston Hollow
  Whitehaven Harbour
  Coalfields Link
  Lancaster Canal
  Kingsand Sea Defence
  Doveholes
  
  MINING
  
  

Mining Face Salvage

 
FACE SALVAGE
 
Introduction:

Both standard welded mesh and "plastic" meshes are commonly used for preparing coalfaces for salvage. This case study relates to the use of plastic mesh reinforced with woven banding in order to improve the overall strength of the mesh panels thereby allowing the safe and efficient removal of the face equipment. Both the mesh and the banding are fully approved for use within an underground coal-mining environment.

The mesh panels are fabricated in lengths of 25m and to each mines particular design and requirements depending on the Managers Support Rules. Once fabricated the completed mesh is folded and secured with colour-coded tie-wraps to ensure that the mesh is unrolled safely and correctly underground.

The mesh is delivered to site folded up (see picture 1) for ease of transport and to allow the mesh to be easily opened out as the face retreats (or advances) to its final stop position.

Installation Procedure:


Prior to taking the mesh panels onto the face for installing it is essential that the face is straight, at the correct grade and horizon.

In conjunction with the Managers Support Rules the mesh is established over the powered supports as they are lowered and advanced. Care must be taken to ensure that the powered support is lowered sufficiently to prevent damaging the mesh.Adjoining rolls of mesh are overlapped and joined together by means of banding, ties or crimps.

After the mesh is established above the supports it should be held back away from the shearer by means of ties or rubber straps.

The shearer then cuts through the face for a prescribed distance to allow the drilling for and installation of roofbolts. >>

<< The correct colour coded tie-wrap is cut to allow the mesh to be unrolled and then temporary support is set to allow safe drilling operations on the face side of the conveyor.
The conveyor and powered supports can now be advanced, care must be taken not to damage the mesh and the heads of the roofbolts. >>
<< The mesh is again held back out of the way of the shearer by means of ties or rubber straps and the cutting cycle is now repeated.
At the face stop position the final row of roofbolts is installed and the face front is bolted to ensure the safe passage of persons along the face. >>

© 2006 Weldgrip Geotechnical , All Rights Reserved