Meshform Logo - Permanent Formwork System
Meshform
Meshform Products

- Meshform
- About Meshform
- Meshform Applications
- A Typical Installation Process
- A Typical Specification Process

- Common Meshform Uses
- Beams, Bases and Pile Caps
- Semi-Raft Foundations
- Man Holes
- Spacing Systems & Accessories
- Spacer Recommendations
- Related Products from Weldgrip
- Weldgrip Geotechnical Products & Services



Download printable PDF

Weldgrip Case Studies

 

Typical Meshform Installation Process

CHECK THE SCHEDULE......

Check that you have a copy of the Meshform Formwork Schedule which is provided with the delivery. This will ensure that the units are used in the correct sequence, correctly placed and also act as a check list making life much easier for the installation team. Minimum equipment is required for installation - as provided in our installation kit.

Welded mesh and laminated Meshform sheets in our factory

1: Fit plastic spacers to the pile cap steelwork, after checkingspacer type and size listed on Groundwork schedule.


Welded mesh and laminated Meshform sheets in our factory

2: Offer up first pre-formed Meshform section to the spacers.

 

Welded mesh and laminated Meshform sheets in our factory

3: Offer up the second pre-formed section of Meshform to the steelwork.

 

Welded mesh and laminated Meshform sheets in our factory

4: Secure both Meshform sections together using tie wire.

Welded mesh and laminated Meshform sheets in our factory

5: Mark out opening area to take joining U-Section beam.

Welded mesh and laminated Meshform sheets in our factory

6: Cut down centre of steel mesh with wire cutters.

Welded mesh and laminated Meshform sheets in our factory

Formwork Schedule


Welded mesh and laminated Meshform sheets in our factory

7: Cut through plastic film in the centre of opening and also along the bottom of the opening.

 

Welded mesh and laminated Meshform sheets in our factory

8: From top of steel mesh cut through every alternate wire to make bending easier.

 

Welded mesh and laminated Meshform sheets in our factory

9: After cutting through mesh along the bottom of the opening bend back to accept beam run.

Welded mesh and laminated Meshform sheets in our factory

10: Offer up U-Section beam into pile cap opening and secure with tie wire.

Welded mesh and laminated Meshform sheets in our factory

11: After fitting spacers on to beam steelwork fit into U-Section & tie to pile cap.

 